DELIVERABLES

WP 1

Multi-Robot Cooperative System Work

D 1.1

Specifications report

Month 6


March 2024 – Sensitive

D 1.2

CAD file of layout

Month 12


September 2024 – Sensitive

D 1.3

Functional multi-robot cell

Month 18


March 2025

WP 2

Intelligent Quality Assessment

D 2.1

Quality indicators

Month 4


January 2024 – Sensitive

D 2.2

Data acquisition nodes

Month 10


July 2024 – Sensitive

D 2.3

AL-enhanced MLOps tool

Month 24


September 2025

D 2.4

RL Impedance control

Month 24


September 2025

WP 3

Data management platform

D 3.1

Overall Data Architecture

Month 10


July 2024 – Sensitive

D 3.2

Data Connectors

Month 18


March 2025

D 3.3

Human-centred UX Design and Evaluation

Month 24


September 2025

D 3.4

COROB platform release

Month 24


September 2025

WP 4

Integration – Cognitive manufacturing

D 4.1

Integration of internal solutions

Month 31


April 2026

D 4.2

Integration of external solutions

Month 31


April 2026

WP 5

Validation and demonstration

D 5.1

Multi-robot cells demonstrated and validated

Month 36


September 2026

WP 6

Open Call & FSTP

D 6.1

Call Announcement and Guide for Applicants

D 6.2

Open Call and FSTP Management report

Report including open call management related tasks, tasks related to the FSTP and learnings from the execution of the third-party projects in the open call

Month 24


September 2025

D 6.3

Report on mentoring services and third-party solutions

Month 24


September 2025

WP 7

Communication, dissemination and exploitation

D 7.1

Dissemination, Communication and Exploitation Strategy

Dissemination, Communication and Exploitation foundation, including the strategic guidance to direct COROB community building activities for broad and durable impact.

D 7.2

Impact Creation Mid-Term Report

D&C&E and community building activities carried out in the first 18 months.



Month 18


March 2025

D 7.3

Impact Creation Final Report

Month 36


September 2026

WP 8

Project coordination and management

D 8.1

Quality Management Plan


Report including the quality procedures of the project.

Month 6


March 2024 – Sensitive

D 8.2

Data Management Plan


Provides the procedures to manage generated data.

D 8.3

Management report 1

Month 8


May 2024 – Sensitive

D 8.4

Mid-term data management plan

Month 18


March 2025

D 8.5

Management report 2

Month 26


November 2025